SUNFLAG IRON & STEEL CO. LTD (SISCO):M/s Sunflag Iron & Steel Co. Ltd., have a unit of DRI Plant having a rated capacity of 150,000 TPA built with overseas technology. However, the plant operation could not be optimised over a long period. In 1991 Sunflag approached OSIL to assist in optimising their operation. OSIL studied their plant parameters, identified the points of non-compatibility and recommended modifications with engineering support. The major modifications suggested are : - Controlled Raw Material Sizing - Coal Slinger System (Coal Injection) - Kiln Operation – Logic - Kiln Discharge System - Improvement in air sealing system and prevention of air leakage - Modification in kiln to cooling drum transition chute to ensure free-flow of kiln-discharge
Within six months of OSIL's association the plant performance improved to a great extent. |